02 December 2008: Welding Torch Sparked Ship Fire...20 November 2008: Fire Causes Damage at Central Wisconsin Cooperative...18 November 2008: Fire ravages Shreveport playhouse...14 November 2008: Human error blamed for China National Games stadium fire...10 November 2008: Fire destroys Neepawa warehouses
Home |Frequently Asked Questions | Loss History | Downloads | Products | About | Contact | Disclaimer
HOT WORK PERMIT
What is Hot Work - Work that involves open flames or sparks, or any other activity that has the potential to generate heat. Sources of heat commonly used are gas/electric welding, cutting equipment, blow lamps/torches, grinding/cutting disks, bitumen and tar boilers.

Managing Hot Work - This means the prevention of all hot work losses and having absolute control over the activity, there are four key steps, Hot Work Permit, Site Preparation, Safe Working and Follow Up Checking.

Issuing Permits - The issue of permits is strictly controlled, hot work permits can only be issued by authorised personnel.

CAN HOT WORK BE AVOIDED - IS THERE ANY OTHER WAY?

PERMIT NUMBER:
CONTRACTOR (Company):
CONTRACTOR (Employee Name):
NOMINATED FIRE WATCHER:
LOCATION OF WORK (Exact):
Date Work to be Completed:
Time:
DESCRIPTION OF WORK:
SPECIAL INSTRUCTIONS:
I declare that the above has been made known to the competent person in charge of the work and consider the above mentioned area to be safe for the competent person to commence work.
Signed:
Date:
Permit Controller:
Time:

Acceptance by competent person prior to commencement

Acknowledge receipt of this permit and understand the precautions & comments described Above. Neither I nor the persons under my control will work on any other activity or location other than those specified Above.
Signed:
Date:
Competent Person:
Time:

Acceptance by Fire Watch person prior to commencement

Acknowledge receipt of this permit and understand the precautions & comments described Above. I will not work on any other activity or location other than those specified in Above.
Signed:
Date:
Fire Watch:
Time:

Final check by Contractor / Employee

After completion of the work:

  • All hot waste materials should be removed and disposed safely
  • All equipment including gas cylinders have been removed
  • Fire protection equipment, sprinkler protection and fire detection have been reinstated to their normal operating status.

Fire Watch has been maintained with regular inspections for a period of 60 minutes after completion of Hot Work as specified under 'General Precautions' on the reverse of this permit (state yes or no, if no give reasons and action taken):

Comments:
I declare that the work described above is complete and the precautions noted above have been complied with. The area has been inspected and is free of fire risk and all tools and equipment have been removed.
Signed:
Date:
Competent Person:
Time:

Completion of Hot Work Permit - Permit Controller

I declare that the hot work permit is now complete, closed and I have received copies of the permit back from the Competent Person. The area has been inspected and is free from risk and all fire protection systems have been reinstated to their normal operating status.
Signed:
Date:
Permit Controller:
Time:

PRECAUTIONS

After reading the following answer yes or no, if NO do not commence work until discussed and resolved with permit controller, PRECAUTION CHECKS SHOULD ONLY BE COMPLETED DURING AN INSPECTION OF THE WORK PLACE.

GENERAL PRECAUTIONS

1. A trained person not directly involved with the work will provide a continuous fire watch in the work area and those adjoining areas to which sparks and heat may spread, during the period of the hot work and for at least one hour after it ceases. The area SHOULD NOT BE left unattended for any period time until one hour after the work is completed.
2. At least two suitable fire extinguishers must be immediately available. Both the personnel undertaking the work and providing the fire watch are trained in their use.
3. Personnel involved in the work and providing the fire watch are familiar with the means of escape and method of raising the alarm and or calling the emergency services
4. Where work is to be carried out on composite building panels (combustible core), an assessment of the combustibility must be made on the insulating or other material behind or forming the core of the panels.
5. Confirm all other contractors/persons on site are aware that hot work is being undertaken and that there is no storage and or application of paints, flammable solvent based materials and chemicals that could be ignited by the work being undertaken.
6. Blow lamps and gas cylinders must only be changed in the open.

PRECAUTIONS WITHIN 10 METRES (MINIMUM) OF THE WORK

7. Combustible materials have been cleared from the area. Where materials cannot be removed, protection has been provided by non-combustible or purpose made blankets, drapes or screens.
8. Flammable liquids have been removed from the area.
9. Combustible floors have been covered with overlapping sheets of non-combustible material or wetted and liberally covered with sand.
10. Floors are swept and free from dust/debris and other potential hazards or accelerants .
11. Protection (non-combustible or purpose made blankets, drapes or screens) has been provided for:
  • Walls and Ceilings of combustible construction or surface finish
  • All holes, including ventilation, other openings in walls, partitions and ceilings through which sparks may pass.
  • Any exposed core of composite panels.
12. Combustible materials have been removed from the opposite side of walls, partitions or panels where heat could be conducted or transferred, especially where these incorporate metal.
13. Enclosed equipment tanks, containers and voids has been emptied and tested, or is known to be free of flammable concentrations of vapour or dust.
14. Equipment for hot work has been checked is in good operational state and is fit for purpose.
15. Have gas cylinders have been properly secured?
16. Is there adequate ventilation in the working area?
17. Resource provided to provide continuous fire watch and for at least one hour following hot work including check 60 minutes after completion to ensure working area, adjacent area including below above, to the side, partition walls, voids and false ceilings are free of smouldering materials and flames.
18. Any automatic fire detection systems have been isolated in the working area before commencement of work

Notice: This permit acts as a guide to completing Hot Work safely, QRIMS accepts no responsibility for any loss resulting from the use of or failure of this permit to control hot work.

IF IN DOUBT - ASK

Quick and complete control of permits and contractors software tool. Click here to watch the guided tourWatch the guided tour Single user 195 multi user 495 annual license
Home | About | Contact | Products | Guides

QRIMS LTD - 5 Acorn Court, Bridge Estate, Wymondham, Norfolk, NR18 9AL, United Kingdom
Copyright 2003 - 2008. © QRIMS Ltd